Amendment to EPA's February 2004 Settlement [March 2010]:
Effective March 18, 2010, EPA's February 2004 administrative settlement with Occidental Chemical Corporation (OCC) has been amended for OCC to take over risk assessment activities and to work with the Passaic River Cooperating Parties Group to conduct modeling as part of the Newark Bay Study. OCC will perform the study under EPA oversight.
Click here for the amendment. Click here for the 2004 AOC.
Final Screening-Level Ecological Risk Assessment [December 2008]:
In order to identify the potential for contaminants within the Newark Bay Study Area to adversely affect ecological receptor populations and to determine whether additional ecological evaluation is necessary, a
screening-level ecological risk assessment (SLERA) was performed. This SLERA includes a conceptual site model, the contaminants of potential ecological concern, and a preliminary exposure assessment performed
using conservative assumptions. Click here to download the SLERA. Click here to download the attachments and appendices to the SLERA.
Phase I and Phase II Field and Data Report Released [October 2008]:
To define the nature and extent of contamination in the Newark Bay Study Area, two phases of work have been performed so far, in 2005 and 2007. Although the data from these phases of work were provided electronically via this website, we are now releasing a report that compiles the Phase I and Phase II data, summarizes the work done, and includes graphical presentations of surface sediment concentrations and maximum sediment concentrations at each sampling location. Click here to download the Field and Data Report.
EPA Approves Report on the Biologically Active Zone: [October 2008]
One of the goals of the Phase I work performed in the Newark Bay Study Area was to estimate the depth of the biologically active zone (BAZ) throughout the different areas of the bay. A draft BAZ Report was produced as a result of the work done in 2005. Based on comments from the government partners, the BAZ Report was revised, and the final report has now been approved. Click here to download the Final BAZ Report.
Phase II RIWP Sampling Results Released [August 2008]:
Phase II RIWP sampling was implemented from October 23, 2007 through December 14, 2007. Fifty-two sediment cores were targeted for sampling, however, two needed to be abandoned due to lack of fine-grained sediment at those locations. The sediment sample analytical results from the Phase II RIWP effort are available in Microsoft Access database format. To download and review the Phase II RIWP analytical data, click here and for the sample location map, click here.